17 East Wheelock Renovations: Progress and Notifications
Construction Update, July 13, 2009
Special Notices:
none
Construction Activity for the next two weeks:
- Exterior trim patch work
- Excavation and concrete work for new terrace
- Interior stair tower & addition rough-in
- Drywall hanging, taping and mudding
Long-Term Project Milestones:
* Occupancy Scheduled for Fall 2009 Term
Construction Update, May 12, 2009
Special Notices:
none
Construction Activity for the next two weeks:
- Interior framing
- Completion of new stair tower & addition footings and foundation walls
- Interior mechanical rough-in
Long-Term Project Milestones:
- Occupancy Scheduled for Fall 2009 Term