17 East Wheelock Renovations: Progress and Notifications

Construction Update, July 13, 2009

Special Notices:

none

Construction Activity for the next two weeks:

  • Exterior trim patch work
  • Excavation and concrete work for new terrace
  • Interior stair tower & addition rough-in
  • Drywall hanging, taping and mudding

Long-Term Project Milestones:

* Occupancy Scheduled for Fall 2009 Term

 

Construction Update, May 12, 2009

Special Notices:

none

Construction Activity for the next two weeks:

  • Interior framing
  • Completion of new stair tower & addition footings and foundation walls
  • Interior mechanical rough-in

Long-Term Project Milestones:

  • Occupancy Scheduled for Fall 2009 Term

Last Updated: 7/13/09