Project Update, August 3, 2007
Placement of the new re-located Moore-Carson walkway has commenced. The
rough grade of the new landscape layout has been achieved as well as
installation of most of the site's storm water drainage features and buried
electrical and data service feeds. Placement of the concrete sub-structure for
the eastern-most seating wall and some of the Haldeman patio walls has
commenced. The first delivery of the finished granite wall panels is expected
by August 3, with installation of certain panels to commence the following
week.
Upcoming Work:
* Mon. - Fri., July 30 - August 3, 7:30 AM - 5:00 PM: Most all sub-grade
preparation work for the entire project concludes. Installation of buried site
electrical and data conduit feeds continues. Installation of additional
Moore-Carson walkway sections continue. Certain wall foundation excavation work
continues. Concrete footing and wall form work commences with steel
reinforcement and concrete installations to follow. Finished granite wall panel
deliveries are expected Fri., July 3 and weekly thereafter.
NOTE - Possible Sat., August 4, site work entails temporary relocation of the
walk way exiting from Kemeny Hall and installation of a new storm drain
structure where the walk way originally existed. If this work can not be
achieved on Sat. it will occur during next week.
* Mon. - Fri., August 6 - 10, 7:30 AM - 5:00 PM: Installation of new storm
water drainage structures along the eastern edge of the project commences by
mid-week. Installation of additional Moore-Carson walkway sections continue.
Additional wall foundation excavation work continues. Concrete footing and wall
form work continues with steel reinforcement and concrete installations to
follow. Finished granite wall panel installations commence with additional wall
panel deliveries expected on Fri., July 10.
* Mon. - Fri., August 13 - 17, 7:30 AM - 5:00 PM: Installation of additional
Moore-Carson walkway sections continue. Additional wall foundation excavation
work continues. Concrete footing and wall form work continues with steel
reinforcement and concrete installations to follow. Finished granite wall panel
installations continue with additional wall panel deliveries expected on Fri.,
July 17.
Project Update, June 5, 2007
Mon. - Fri.. , June 11 - 15, 7:30 AM - 5:00 PM: Construction site fencing is
installed - PEDESTRIAIRED - PLEASE PAY ATTENTION TO ALL DETOUR SIGNAGE. Final
removals of all Bradley/Gerry underground utilities continues. Continuing
excavation work for the Berry/Carson fire lane commences. Somewhat elevated
noise and vibration levels are to be expected with this work. PLEASE PAY CLOSE
ATTENTION TO THE GENERAL NOTE ON CONSTRUCTION VEHICLE ACCESS - ABOVE.
Mon. - Fri., June 18 - 22, 7:30 AM - 5:00 PM: Excavation work for the
Berry/Carson fire lane continues. Excavation in-fill of the landscape bowl area
continues. Somewhat elevated noise and vibration levels are to be expected with
this work. PLEASE PAY CLOSE ATTENTION TO THE GENERAL NOTE ON STRUCTURAL STEEL
DELIVERIES - BELOW.
**** IMPORTANT GENERAL NOTES ****
PROJECT SIGNAGE - Please pay close attention to all project-related signs
posted around the project perimeter and alerting everyone to site condition
changes and safety issues, including building access routes. These signs are
provided for everyone's benefit and safety. If anyone does NOT want to remain
on this mailing list please let me know.
GROUND VIBRATIONS - Some ground vibrations may occasionally be felt with
different construction activities but these are typically not of the type to
cause structural problems within buildings. Loose items within buildings may be
effected by these vibrations and possibly rattle and/or shake a bit.
CONSTRUCTION VEHICLE ACCESS - Please pay attention to contractor vehicles
within the construction site and crossing the cross-way exiting from Kemeny
Hall. These vehicles will be escorted by construction crew personnel - PLEASE
PAY ATTENTION TO THEIR DIRECTIONS. Please also pay attention to contractor
vehicles which continue to access and leave the construction site via the
Maynard St. entrance adjacent to Moore Hall.
DETOURS AROUND THE CONSTRUCTION SITE - For the duration of this project
(Sept. '07) the main walkway running between the Berry/Carson building and
Moore Hall will be closed to pedestrian foot traffic. Pedestrian detour routes
are via the sidewalks of either No. Main St. or College St. as shown on the
enclosed Kemeny Walkway Detour PDF map. People exiting the lower level of
Kemeny Hall can use a temporary cross-walk passing through the construction
site and over to the parking lot of the United Church of Christ - PLEASE USE
CAUTION AND PAY ATTENTION TO ALL ADJACENT CONTSRUCTION ACTIVITIES WHEN USING
THIS CROSS-WALK.
WHOM DO I CONTACT?
For construction questions and concerns write, fax or call the Dartmouth
College Representative:
Bill Kitchel, Project Manager
Dartmouth College, Facilities Planning Office
TEL. (603) 646-0570
CELL (603) 359-3248
FAX: (603) 646-3235
email: Bill.Kitchel@Dartmouth.edu
Matt Purcell, Assoc. Director
Dartmouth College, Facilities Planning Office Office
TEL. (603) 646-1499
FAX: (603) 646-3235
email: Matthew.R.Purcell@Dartmouth.EDU
DANIEL O'CONNELL'S SONS (DOC)
Main Office TEL. (781) 642-0660
Wes Hastings, Project Superintendent On Site
TEL. - 646-6601
FAX: - 646-0257
FOR EMERGENCY SITUATIONS ONLY
Safety & Security
TEL. (603) 646-2234
|