Construction Update, May 3, 2007
Some demolition continues with underslab excavation for new footings and pipes. Work continues on the plywood subfloor, partition framing, and electrical rough-in.
Construction Update, April 16, 2007
The contractor is installing floor underlayment and framing, and working on basement floor demolition.
Construction Update, February 23, 2007
The abatement and demolition contractor, Dec-Tam, has completed abatement and demolition, leaving the interior stripped down to brick, concrete, and steel. Small amounts of interior work are ongoing as Pizzagalli Construction Company reviews bids and begins to mobilize on site.
Please note that the walkway between Gile and Hitchcock will be modified to improve drainage soon.
Construction Update, January 15, 2007
The hazardous materials abatement is proceeding ahead of schedule, and should be completed by February 1, 2007. There will still be odds and ends of clean demolition and cleanup to take care of after that, and when those last pieces are complete, actual construction will commence.
Construction Update, November 27, 2006
The building is currently undergoing abatement, after which the interior demolition and renovation will begin. Construction fencing has been installed, along with a temporary walk between Hitchcock and Gile Halls.
DARTMOUTH COLLEGE
Andrew Ager, Project Information Manager
Office of Planning, Design & Construction
TEL. 603.646.9290
FAX 603.646.3235
EMAIL Andrew.D.Ager@Dartmouth.edu
Win Chambers, Project Manager
Facilities Operations & Management
TEL. 603.646.2825
EMAIL Winston.H.Chambers@Dartmouth.edu