Alumni Gymnasium Renovation

Alumni Gymnasium Fitness Center

 

Type Of Project:

 

Athletics Renovation

Construction Cost:

 

$12,815,000

Start of Construction:

 

April 2005

Occupancy:

 

November 2005 - August 2006

Architect:

 

LaVallee/Brensinger Architects

Construction Manager:

 

North Branch Construction, Inc.

The renovation of Alumni Gymnasium entailed the following work:

  • Installation of a dehumidification system for the Karl Michael Pool
  • Reconfiguration of some of the pool seating and coaching staff offices into a dividable 1,800 square-foot multi-purpose space, overlooking the Karl Michael Pool
  • Installation of a four-stop elevator making all levels of Alumni Gym handicap accessible
  • Creation of a 14,000 square-foot state-of-the-art fitness center for all Dartmouth students, staff, and community
  • Installation of a new air conditioning system throughout all of Alumni Gym and the Manley Building
  • Reconstruction of the roof over Alumni Gym and Manley
  • Reconfiguration of the main entranceway into Alumni Gym from Wheelock Street to provide for ADA accessibility
  • Creation of a new equipment distribution room and office along the corridor connecting Alumni Gym with the Berry Gym
  • Fire sprinkler system throughout all of Alumni Gym and Manley
  • Creation of three multi-purpose rooms in Manley. The two large rooms (3,500 square feet each) are equipped with an operable division wall to allow programming of five separate multi-purpose spaces in Manley.

Work was completed in August 2006, with the pool having been finished in November 2005, and the Fitness Center in April 2006.

 