Buchanan Hall Renovation : : Progress and Notifications

Construction Update, July 13, 2009

Special Notices:

none

Construction Activity for the next two weeks:

  • Construction of Connector into Woodbury
  • Painting
  • Millwork and Carpet Installation
  • Plumbing, Mechanical, and Electrical Work
  • Installation of Elevator

Closures and Access Issues:

none

Long-Term Project Milestones:

Occupation of office by September 2009

 

Construction Update, May 12, 2009

Special Notices:

none

Construction Activity for the next two weeks:

  • Construction of Connector to Woodbury
  • Interior construction of plumbing, HVAC and electrical systems
  • Completion of wallboard installation on 1st and 2nd Floor
  • Plaster on 2nd and 3rd Floors

Closures and Access Issues:

none

Long-Term Project Milestones:

Occupancy Scheduled for Fall 2009 Term

 

Construction Update, January 26, 2009

Special Notice:

Continued use of abatement equipment located on the north side of Buchanan.

Construction Activity for the next two weeks:

  • Continued asbestos abatement
  • Selective demolition

 

Construction Update, January 6, 2009

Special Notices:

Hazardous Abatement using outdoor equipment will begin around January 12, 2009. This equipment will run between 7:30 and 5:00pm. The compressor that runs the equipment does generate noise. This equipment will be used for approximately 4 weeks.

Construction Activity for the next two weeks:

  • Contractors mobilizing on site
  • Electrical and mechanical demolition
  • Selective demolition
  • Hazardous material abatement

 


Long-Term Project Milestones:

  • End of abatement - February 2009
  • Renovations start - February 2009
  • Exterior construction starts - April 2009
  • Move-In - September 2009

 

 

Last Updated: 7/13/09