Construction Update, August 28, 2008
Astroturf material is currently being installed, with a completion date of August 29. Fencing will be finished by September 4, along with the water reclamation pump system.
Construction Update, July 18, 2008
The irrigation system has been installed and the sand layer placed on Chase 4 Field in preparation for sod placement in late July.
Chase 3 has irrigation in place and stone base being installed in preparation for E-layer (the astroturf base material) being installed in late July to early August.
All work is currently on schedule to have the fields playable by September 1, 2008.
Construction Update, June 12, 2008
Fence posts are installed for the new field alignment. Field underdrains are being installed along with perimeter drainage piping. Initial concrete pours are taking place on the stormwater reclamation tank. A stone base and E-layer will be installed in coming weeks in preparatation for the artificial turf installation in August.
|