|
Review Comments: The EPA/ADL Presentation at CAG Meeting January 23, 2002
I was unable to attend
the meeting, but I have reviewed the written material presented by EPA
and have exchanged Emails with Ed Hathaway to request additional data and
to clarify several issues. These data, consisting of detailed spreadsheets
describing the development of the new O&M costs have been sent to me by
ADL.
At the meeting, the EPA presented: (1) The reports
by their experts who had reviewed the EE/CA report and actually visited
the site in November 2000, (2) a "new" treatment sequence for TP3 if it
is decided to preserve the entire site, or a portion of the site, and (3)
revised costs for the entire project, these included a large and rather
startling increase in operation and maintenance (O&M) costs for the TP3
treatment system.
The acronyms for the various treatment system
components in this project are becoming somewhat confusing and the number
seems to grow with each iteration. At the end of this report, I've made
a list of the acronyms, and some of the other critical technical terms,
in current use with a brief description of each.
(1) Expert's Review
These individuals included five internationally
recognized consultants with significant experience in acid mine drainage
(AMD) work, an expert from the U.S. Geological Survey, and an engineer
from a company with experience in constructing and managing corrective
action at AMD sites. All of these people have reviewed the draft EE/CA
report and inspected the site. Their comments can be found in the report
"Elizabeth Mine Engineering Evaluation/Cost Analysis Comments and Technical
Review Reports," presented at the January 23rd CAG meeting. The two Technical
Advisors to the CAG had previously reviewed the draft EE/CA report and
also offered comments.
It is the consensus professional recommendation
of all of these qualified reviewers that the tailings piles at TP3 should
be removed completely. The reason behind this consensus opinion is the
presence of the highly acidic seepage containing high concentrations of
metals. This seepage will be very difficult and expensive to treat. However,
because of the local interest, options were presented for retention of
TP3 and treatment of the seepage. There was no consensus by the experts
on the proposed treatment (ALD followed by a SAP
followed by an aerobic wetland in the draft EE/CA report). The majority
believed the proposed system would not perform as intended without excessive
operational and maintenance attention and costs. I shared those concerns.
As a result of these concerns the EPA then tentatively
proposed SRB's instead of SAP's. Concerns were then expressed because of
the high iron and aluminum concentrations in the TP3 seepage. A significant
amount of these metals might be separated within the SRB, this in turn
would result in clogging of the bed resulting in failure and/or requiring
very frequent maintenance. To overcome these problems, a third iteration
of the TP3 treatment sequence has now been proposed, and will be described
and discussed below.
The fact that we are in the third iteration of
a possible treatment sequence should not be taken as a criticism of EPA
or ADL. Such changes are normal in the development of most engineering
designs and it should be remembered we are still in the conceptual stage
on this project. However, the fact that we are now at the third iteration
is strong evidence of the difficulty of treating the acidic TP3 seepage.
As noted in my comments below, I still have reservations regarding the
ability of this "new" system to perform reliably on a year-round basis
here in Vermont. It is possible that the system which is finally selected
could be even more complex and more expensive.
Acid mine drainage has been successfully treated
at a large number of locations in the U.S., with some systems being operated
for over 20 years. These, however, are mostly coal mining operations and
do not contain the very high concentrations of the types of metals present
in the TP3 seepage. The treatment sequence now proposed for TP3 has not
been used at any other site, to my knowledge. Some of the components have
been in successful use for three to six years (an exception is conventional
aerobic wetlands, these have been used for many
decades), but there is no experience with the long term period required
at TP3. The revised projections to 100 and 200 years, instead of the typical
30 years used at most engineering projects, are valid. I cautioned in my
first review of the draft EE/CA report that O&M would be required for "generations,"
apparently the EPA now concurs. The rock particles in the TP3 tailings
piles have been exposed to the environment for many years already and the
seepage is still highly contaminated. These rocks will not be "clean" in
the near future, contaminated seepage will continue until the acidic tailings
piles are almost completely dissolved, or completely covered, or removed.
top
The "New" Treatment Process for TP3
This new treatment sequence has been developed
to solve perceived problems with the earlier proposals. Both the SAP's
and SRB's are in some ways similar to a filter bed. The water passes down
through the media and biochemical transformations occur which then permit
the settling and separation of metals in the unit or in subsequent components.
In the case of TP3 seepage, the water has very high concentrations of aluminum
and iron, and may also contain significant dissolved oxygen. These factors
could allow the precipitation of aluminum and iron inside the SRB
resulting in unacceptable clogging. The EPA consultants now believe it
will be necessary to remove the iron and aluminum prior to the SRB, so
we now have a SPAD (Semi Passive Alkalinity Doser),
a mixing channel, and a settling pond ahead of the SRB unit. As the name
implies the SPAD is semi-passive and uses a water wheel to drive the feed
mechanism for adding an alkaline substance to the water. The increase in
alkalinity allows the iron and aluminum precipitation
reactions to begin; the mixing channel, probably lined with coarse rocks
to induce turbulence, insures high oxygen levels in the water so the iron
and aluminum can oxidize, precipitate, and settle out in the settling pond.
This reduces the SRB clogging potential considerably, and the water then
passes through the SRB for removal of copper, lead, zinc and cadmium. Effluent
from the SRB then runs down an aeration channel to the wetland. The purpose
of this rock lined aeration channel is to increase the oxygen content of
the water before it enters the wetland. The final component is the aerobic
wetlands. The wetlands are planned for BOD and manganese
removal with a "combination of rock filters and algae mats." Details were
not provided on the configuration of these features but it is indicated
that manganese oxidation will occur by contact with algal mats of leptothrix
discophora algae. In accordance with federal and Vermont standards
the water at the end of the treatment system discharge pipe, prior to any
mixing or dilution in a stream, would be the point of compliance measuring.
The cost estimates provide an allowance for sampling and testing.
It is indicated that all of these components
are in use at ADM sites elsewhere. For example, a list is given of 19 sites
where the SRB unit is in use. Scanning the list indicates that 17 of these
systems are pilot scale, or even smaller "bench" scale units. The one full
scale application, at a mine in Missouri, designed for lead and zinc removal,
has been in operation for up to 5 years. We have a much more severe winter
climate than Missouri so extrapolations are not possible. A pilot test
of the entire proposed treatment process at the Elizabeth Mine would be
absolutely essential prior to final design.
I am still concerned about the impact of our
winter conditions on the proposed system, both on performance and on the
ability to function at all. The design cannot assume that Global Warming
will convert our climate to the equivalent of Pennsylvania's or Missouri,
if the system is expected to run continuously throughout the winter it
must contend with worst case conditions. Based on 42 years of record at
the Lebanon, NH airport, the coldest winter in the Upper Valley occurred
in 1970, the average January temperature was 18°F, in February 21°F,
and in March 31°F. The extreme temperature in January was - 28°F.
Under these conditions, with three continuous months of sub-freezing weather,
ice will certainly form on all of the ponds, on the wetlands, and on the
mixing and aeration channels. The latter are most susceptible to icing
and a long period of sub freezing weather could result in creation of an
ice glacier and subsequent overflow from the channels. It is also unclear
how the algae in the wetland can perform their intended function at expected
winter temperatures and under an ice or snow cover on the wetland since
either ice or snow cover on these wetlands will occur every winter, and
the algae require exposure to sunlight to function. It is true that a deep
snow pack will act as an insulating barrier and retard freezing. The ground
in my front yard will remain unfrozen if we get an early snowfall in November
and the snow persists and accumulates all winter. That, however, is not
the typical case. We more often have a cold December and no snow until
January. The most reasonable solution for TP3 treatment might be to design
this system for seasonal operations, say from early April to late November,
with the seepage being stored in the holding pond during the colder months.
top
I also have concerns about the summer performance
of the proposed wetland. It is not quite the same as the typical constructed
cattail marsh used at many coal mine AMD sites. The wetland is to have
rock cobbles on the bottom, presumably to provide the surfaces for the
algae to attach and grow, and at least three species of plants will be
planted. However, the algae require exposure to sunlight and if the plants
grow and multiply they will shade the water surface, and without sunlight
the algae will die. These aquatic plants also die back each fall, if the
litter is not harvested, and removed, it may smother the algae. Apparently
the algae mat for manganese removal is being proposed since the familiar
cattail marsh is not too effective for removal of this metal. I have no
personal experience with using algal mats, but am aware they have been
demonstrated in Florida and California and achieved excellent removals
of phosphorus and metals. Those systems incorporated frequent algae harvesting
because if the algal cell is allowed to die and decompose there is a release
of substances back into the water. Algae harvesting would not be feasible
at Elizabeth Mine. Algae also require nutrients (ie: nitrogen, phosphorus,
etc) to grow and function. Such nutrients are not normally present in the
ADM waste flow, but may leak in sufficient quantities from the SRB component.
Another proposed wetland function is removal
of BOD, because the SRB will leak organic material as BOD (Biochemical
Oxygen Demand). The concentration may be significant for three to six months
and stabilize at 10 mg/L according to the EPA handouts. A 10 mg/L BOD concentration
is already below typical discharge standards in Vermont so it is unclear
why the wetland is needed for this purpose. In my experience, a wetland
system will discharge from 6 to 8 mg/L BOD as a "background" level due
to the decomposition of natural organic materials present in the wetland.
The title "Aerobic Wetland" may also be a misnomer.
The term "aerobic" implies the presence of oxygen. It has been my experience,
that in constructed wetlands with water depths of one foot or more, only
the water very near the surface has any oxygen, the bulk of the water in
the wetland is essentially devoid of oxygen (or "anoxic"). If the water
depth is limited to a few inches the entire depth may be "aerobic." In
the winter time, after ice forms, even the surface layer of water in the
deeper wetland is essentially devoid of oxygen, except near the front end
where the water enters. The "new" treatment sequence proposes the use of
an aeration channel ahead of the wetland in order to increase the dissolved
oxygen in the water entering the wetland. It has been my experience, with
wetland systems elsewhere that such oxygen will be rapidly utilized near
the front end of the wetland and will not contribute to aerobic conditions
in the remainder of the wetland.
In summary, I still have reservations about the
ability of the "new" TP3 treatment system to provide all of the intended
treatment responses and to even function effectively in the Vermont winter.
I believe the most prudent choice may be to completely remove the tailings
piles at TP3. However, if it is decided to preserve all or part of TP3
I also believe a functional treatment system can be developed after pilot
testing. Such a system will be very complex and very expensive to operate
as evidenced by the increasing cost estimates presented so far by the EPA.
top
Cost Estimates
The most recent cost estimates for operation
and maintenance of a TP3 treatment system have risen dramatically. Sufficient
details were not given at the January 23rd presentation so it seemed desirable
to review the estimating data and procedures carefully to be absolutely
sure the numbers were valid. I asked the EPA for such data and it was immediately
provided by ADL. It consists of a massive (>5000K) multi paged spread sheet.
This spread sheet contains a preliminary sizing of the various treatment
components, made by the consultant engineers, estimates of the materials
and labor and costs required for construction and estimates of costs for
operation and maintenance (O&M). A one page summary of O&M costs was also
provided and a hard copy of this is now on file at the Copperas Hill Coalition
(Kathy Hardy). I have reviewed all of these these data and conclude that
the projected costs are valid and realistic and were developed using standard
procedures. It must also be remembered that we are still in the conceptual
design stage and any cost estimate at this point is at best valid to within
about 20 percent of the real costs. It is likely that as we get closer
to the final design these costs will continue to change and are likely
to get even higher. As an example of the estimating procedure I have presented
below more detailed values from the ADL spread sheet to demonstrate where
one of the summary costs presented by EPA came from.. The O & M (called
PRSC costs by EPA & ADL) include two major components, the actual annual
costs that occur every year and recurring costs that occur on a less frequent
schedule. In the latter category, for example, would be replacement of
the media in the SRB. A more realistic replacement schedule of 10 years
has now been adopted in the ADL estimate. The original, somewhat optimistic
schedules ranged from 15 to 25 years, but there was no actual experience
to back up those estimates. I objected to that in my original review and
believe the 10 year cycle is more realistic. Another major change from
the draft EE/CA report is the assumed life cycle cost period. As with most
conventional engineering designs the draft report assumed a 30 year period.
In my review at the time, I indicated the O&M costs would continue for
generations. EPA now agrees and has assumed a period of at least 100 years
for costing purposes. This means that the recurring costs will be repeated
10 times over the 100 year period instead of just once with the 30 year
assumption.
The actual estimated annual costs, assuming a
non-hazardous sludge, for TP3, include:
| Labor for system operation |
$36,972
|
| Lime purchase for SPAD |
$3,733
|
| Sludge management labor |
$5,688
|
| Misc. sludge management costs |
$2,370
|
| Road & parking maintenance |
$2,370
|
| Sampling |
$14,220
|
| Sludge disposal |
$10,665
|
| |
$101,330 per year
|
The recurring costs occur on a ten year cycle,
the present worth of these costs is determined and then distributed as
an equivalent annual amount. These annualized amounts are:
| Wetland draining and replacement |
$10,586
|
| SRB drainage rock 425 SRB organic
material |
1,316
|
| SRB - piping |
1,322
|
| SRB liner |
4,424
|
| SRB - excavation to rebuild |
2,370
|
| Holding pond dredging |
113,586
|
| SRB sludge disposal |
18,971
|
| |
$153,000 per year
|
| |
|
When you add these two sets of costs, the total
is $254,330 which is the same as the summary value for the complete preservation
of TP3 with a non-hazardous sludge, presented by EPA at the November CAG
meeting. The annual O&M costs for a hazardous sludge were $400,000. At
this stage, I think it would be conservative and prudent to assume that
the sludge requiring disposal would be hazardous. Hopefully, information
would come from a pilot test to define sludge characteristics.
In summary, I believe these cost estimates are reliable for this stage
of conceptual planning, and were derived using appropriate methods.
Sherwood
C. Reed, P.E.
Principal, E.E.C.
top
GLOSSARY
AEROBIC WETLAND
A constructed marsh with growing plants. For most coal mine systems this
is often a simple cattail marsh. For TP3 a rock substrate to support algae,
and plants are proposed. These wetlands are used for final polishing of
the water. Some kind of wetland is a likely component for both TP1/TP2
and TP3.
ALD
Anoxic Limestone Drain. A deep trench, filled with limestone. The trench
is covered with a clay cap to prevent the entrance of oxygen, hence the
term "anoxic." seepage enters through one wall of the trench and passes
out the other. During the time the water is in the trench it acquires alkalinity
from the dissolving limestone. This alkalinity permits metal precipitation
at a later stage. An ALD may be used in the treatment sequence for TP1/TP2.
ALKALINITY
An alkaline water contains carbonates or hydroxides, highly alkaline waters
are called "hard" and can precipitate deposits on your teapots and cooking
vessels. Water softeners are used to remove this alkalinity from hard waters.
Acidic mine waters tend to have very little alkalinity and this prevents
the precipitation reactions that allow metals removal. It is typically
necessary to add alkalinity to such waters to allow treatment.
BOD
Biochemical Oxygen Demand. A laboratory test of water quality. An indicator
of the amount of degradable organic material in the water.
LEPTOTHRIX DISCOPHORA ALGAE
A species of algae which attaches to surfaces on the bottom of streams.
Has been shown to be very effective for removal of some metals. Requires
sunlight, and nutrients to live and function.
SAP
Successive Alkalinity Producing system. A shallow pond containing a layer
of limestone on the bottom overlain by a layer of compost, with underdrain
pipes located in the limestone layer. The mine water passes down through
these layers where biochemical reactions increase the alkalinity and prepare
conditions for precipitation of metals in the next treatment unit (typically
the wetland). The underdrain pipes alos are used to flush the bed periodically.
The SAP is a possible treatment concept for TP1/TP2.
SPAD
Semi Passive Alkalinity Doser. This is a tank containing limestone chips
or pebbles, or some other alkaline chemical. An attached water wheel drives
the feed mechanism so the does of chemical is compatible with the amount
of water flowing by. The purpose is to provide sufficient alkalinity to
permit the removal of iron and aluminum in a settling pond. A possible
treatment unit for TP3.
SRB
Sulfate Reducing Bacteria bioreactors. The SRB is similar to the
SAP in that water flows downward through the media. But in this case the
media largely consists of high strength organic material, such as raw cattle
manure which contains sulfates. The bed is devoid of oxygen and the biochemical
reactions produce metal sulfides which then settle out. Wood chips, alfalfa
hay, and other organic materials have also been used. Limestone gravel
is usually included in the mixture to improve permeability and provide
a supplemental source of alkalinity. The SRB is susceptible to plugging
if high concentrations of iron or aluminum are present in the water. An
SRB is now proposed for TP3, after the iron and aluminum have been removed.
top
|