Elizabeth Mine Community Advisory Group Meeting

Barrett Hall, South Strafford

September 24, 2003 Meeting Summary

Approved ­­­­­­­­­­­­­­­­­­­­­­­­­May 12, 2004

 

EMCAG Members and Alternates Present: Deby Botelho, Linda Cook, Tom Essex, John Freitag, Neal Meglathery, Gwenda Smith, Scott Stokoe, Bob Walker and Steve Willbanks

Copperas Hill Coalition: Fred Moody

VT Agency of Natural Resources: John Schmeltzer

EPA:  Ed Hathaway, Bill Lovely and Steve Novick

U.S. Army Corps of Engineers: Scott Acone

URS: Jason Clere and Chris Hatton

Copperas Hill Coalition: Lori Barg, Anne Clift, Dick McGaw, and Fred Moody

Adamant Accord: Cindy Cook, Facilitator

 

 

Update of Site Activities

Ed Hathaway reported that EPA is taking samples at the site this month, and that the team is working with the Strafford and Thetford Selectboards on ways to reduce traffic impacts associated with the emergency stabilization work.

 

Traffic levels for the installation of a diversion pipe will be similar to the truck levels in April, when the filter was installed.  The second part of the stabilization work—the construction of a buttress—involves significantly more truck traffic.

 

The truck route that was agreed upon with the Strafford Selectboard is VT Route 132 to Tyson Road to Mine Road.  Almost all of the trucks will bypass South Strafford village.  Ed noted that site activity will increase over the next few weeks.  Most of the traffic for the diversion pipe will run in mid to late October, and if all goes well, hauling of material for the buttress will begin in November and continue until weather conditions shut down operations.

 

In response to a question, Ed stated that while nothing is off the table, the construction of a new access road would be time-consuming to complete.  While an access road might be justified if the entire cleanup is funded, it is difficult to justify the expense for this limited emergency work.

 

John Freitag asked why erosion control measures were not more extensive for the work that was completed earlier this year.  Ed responded that the entire site is eroding rapidly, and that he doesn’t think that the work that was done earlier this year exacerbated the problem.  His team has removed dump truck loads of eroded material from the weir at the base of TP-3.  Scott Acone added that he inspected the site earlier in the day, and the areas where his team worked were not eroding.

 

John Schmeltzer reported that he met with representatives of the Vermont Agency of Transportation (AOT) earlier in the day, and their initial assessment was that the welded joint in the Tyson bridge was sound enough to handle the truck traffic associated with the emergency work. AOT based its calculations on 55-ton trucks, and will recalculate, based on the larger (70-ton) trucks that are now proposed.  AOT will conduct inspections of the bridge during and post construction.  ANR is committed to working with EPA and AOT to repair any damage to the bridge resulting from the emergency construction traffic.

 

EPA committed to inspecting houses within 25 feet of Tyson and Mine Roads, and will repair any damage directly attributable to traffic related to the emergency work.  John Schmeltzer said that they would also inspect the roadways before and after the project.  ANR has asked that AOT have an inspection team present on VT Route 132 to periodically inspect trucks and to be a presence during project work.

 

John Freitag noted that there will be flaggers at both ends of Tyson Road to control truck traffic, there will be a meeting before work begins to review safety measures, and that the Strafford Selectboard has asked that the Orange County Sheriff’s Department patrol VT Rout 132 regularly.  He also suggested the development of an e-mail list to address traffic concerns.

 

There was some discussion regarding whether or not truck restrictions on Tyson Road would apply just to the EPA trucks, or to local trucks as well.  Ed noted that the flaggers would only be responsible for EPA project trucks, but they may ask that local trucks stop briefly to allow school busses to pass.  He asked for fairness -- while the emergency construction will generate a significant number of trucks, EPA trucks traveling on Tyson Road are no more dangerous than the service trucks, logging trucks and other local contractors’ trucks that use Tyson Road on a routine basis.

 

In response to question, Scott Acone stated that trucks will be covered while traveling both to and from the site.  In response to a concern from the Thetford School Board, Ed agreed that truck traffic will be minimized on VT Route 132 between Tucker Hill and Tyson during the times that school buses travel this part of Route 132.  Ed noted that to do this, he needs the Thetford school bus schedule, which he has asked for, but still has not received.

 

Bob Walker asked that drivers be asked to minimize idling of their vehicles, as it results in air pollution.

 

Peggy Thorp and others noted that the 6:50 Thetford school bus travels on Mine Road at unsafe speeds.  Neal said that he would relay this concern to the Thetford Selectboard.

 

In response to a question, Scott Acone stated that Conti Environmental is the firm that will do the construction work.  They have not yet hired a subcontractor.  Scott will circulate a contact list for concerns regarding the construction work.  He noted that their contractor is obligated to follow the Army Corps’ direction during construction, including adherence to the traffic safety plan.

 

Ed and Steve Novick stated that they will prepare a project Health and Safety Plan that addresses the concerns of the Strafford and Thetford Selectboards, as well as those of the Newton School Principal.

 

Linda Cook asked if surrounding towns should communicate directly with EPA, or work through the Strafford Selectboard.  Ed stated that he would prefer that each town communicate directly with EPA.

 

Lori Barg noted that active treatment is planned for the buttress construction work next spring, and suggested that active treatment also be used this fall, while the pond on TP-1 is being drained.  Other than that, she thinks that the design of the diversion pipe is fine.  Dick and Anne both noted that they are happy with the diversion pipe design.

 

Ed noted that he is concerned about safety issues during construction.  He is working with the landowners to secure the site, and to provide opportunities for controlled site visits, to ensure everyone’s safety.

 

Lori Barg asked for more time to review draft meeting summaries and engineering designs.  Cindy noted that the drafts were circulated for the EMCAG’s review several months ago. Scott responded that the project schedule is tight, and the project team presented plans to Lori that afternoon because they had just been completed.

 

 

CHC Update

Fred Moody noted with sorrow the death of Woody Reed.  He asked if the EMCAG wants to seek another wetlands expert, and if a traffic expert is needed.  He also raised the possibility of hiring an expert to oversee the foundation inspections.

 

Scott Acone explained that the inspections are pretty straightforward.  They involve video documentation, and measurement of existing conditions, including foundation angles.  The engineering judgment comes in analyzing the cause of any changes.  Steve Novick noted that the houses that will be inspected are private property, and that if CHC hires an engineer to oversee the inspection work, the person hired will need to make his or her own arrangements for access.

 

John, Steve, Tom and Neal expressed support for hiring a CHC advisor to oversee the foundation inspections.  Bob, Scott, Deb and Linda stated that they did not feel that CHC funds should be used for inspection oversight, and noted that they hoped that another source of funds could be found to give homeowners assurance that the inspections would be conducted carefully and professionally.

 

Lori asked what the sand that will be hauled to the site this fall will be used for.  Jason stated that it would be used for a sand filter on the face of the buttress to provide drainage.  The main body of the buttress will be glacial till.  A location for the stockpiled material has not yet been chosen.

 

Review of April 16, May 28 and June 25 Meeting Summaries

The April 16, May 28 and June 25 Meeting Summaries were approved with minor revisions.

 

Election of Officers

Steve Willbanks and Linda Cook were nominated for the position of Vice Chair.  The Vice Chair will become chair on December 11.  Steve Willbanks was elected Vice Chair.  Gwenda Smith was re-elected Secretary, and Deby Botelho was elected             Treasurer.

 

Next Meeting

The next EMCAG meeting will be on December 10th.

 

The meeting was adjourned at approximately 9:00.