SUMMARY OF MEETING
WITH URS, EPA, USACE, DEC AND STEP BY STEP
August 11, 2003
Attending: Jason Clere,
Ed Hathaway, Scott Acone, John Smeltzer, Lori Barg
Agenda:
- Data Transfer
- Comments Regarding Emergency Funding
- Review Of Diversion Pipe Hydrology And
Design (To Tag By 8/22)
1. Data Transfer:
The EPA et. al. will provide me with copies of the following electronically
(if possible):
- The SLERA report appendices as an excel
file (received successfully).
- Jeannie Kornfeld/Bob Seal’s loading data,
this is the only year-round loading data available.
- Chemistry of seeps at base of TP1, breakdown
of types of iron (reduced or oxidized) and pH of these seeps.
2. Emergency Response Concerns
I raised 5 points in my Emergency Response
review. As anticipated, these are mostly being addressed. They
were:
- Buttress: They have not performed
calculations on residence time, but it is likely that the residence
time will not be substantially changed (that means that chemistry
of seeps will not substantially change), but it is likely that
in the end, flows will be reduced from seeps. They will look
into active treatment during construction to reduce the
chance of acid shock to the system per recommendation.
- Foundation of buttress: They have
mapped lateral extent of tailing fan, and have measured depth
of tailing fan. The thickest part of the fan is towards the
base of TP1. They plan on removing part of the tailing fan
as part of building the buttress. I requested that they try
to remove the whole tailing fan as part of this action. The
horizontal and toe drains will all be diverted to a single outlet,
and the water from that outlet will be directed so that it does
NOT flow over the tailing fan. The effluent will probably be
directed into a settling pond or something similar for the iron
to precipitate out, and then channelized through the remaining
tailings. The ANR will be responsible for O and M. I strongly
recommended that they try to remove the entire tailing ‘fan’
at the base of TP1.
- Diversion: See Figure 1 and Table
1. We talked about the diversions that could be performed by
both the Town of Strafford and EPA. Figure 1 shows recommended
areas for Strafford to divert water (stars on map). The most
important areas are uphill and downhill of TP3 along Copperas
Road (the class 4 road) and diverting the stream from subwatershed
1 that mixes with the TP3 tailings just upstream of Mine Road
into the culvert nearby. This is especially critical at the
drainage of subwatershed 1 by the Mine Road, where a good part
of the clean watershed mixes with the runoff from TP3. The
Town could berm, or divert the flow into the culvert that is
a couple of hundred feet down the road. The flow would still
need to be diverted below the tailings that are upstream and
downstream of the Mine Road culvert.
Key:
Blue line = diversion on east side of TP1/2
Red line = diversion on west side of TP1/2
Black line = Mine Road
Thin blue line through watershed 4 and 7 -Jeep Road that will
be used to bring fill to base of TP1 for buttress
Thin Blue Line, watershed 1 and 9, Class 4 Copperas Road through
TP3.
Star = critical area for Town of Strafford to divert flow
to keep clean water from mixing with tailings.
|
Table 1: Sizes of sub-watersheds (ADL)
Sub
watershed
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
12
|
Total
area (acres)
|
86
|
30
|
26
|
26
|
15
|
7
|
27
|
4
|
2
|
29
|
22
|
6
|
If you look carefully at the map, you
will see that uphill of all the roads is quite a lot of clean
watershed, the roads almost make a diversion ditch surrounding
TP1 and TP2. in other words, with some careful consideration
of ditching and culverts to keep the ‘clean’ water from mixing
with the tailings, there is a lot of this clean watershed that
will not mix with the tailing piles. There are more roads on
the map than are shown. Near the buildings at the lower part
of watershed 4 and 11 there are several driveways, careful ditching
of these driveways can prevent clean water from mixing with the
tailing. I recommended that both the Town and EPA look carefully
at all the roads and culverts on the map, including the Jeep Road
and the multiple roads that go down to TP1 and take every opportunity
to re-ditch, install culverts etc. to keep the ‘clean’ water from
mixing with the tailings. Jason offered to walk the roads and
do a quick stormwater culvert map. This would help to determine
the quick, easy solutions to diversion. The EMCAG should support
this stormwater mapping. John Smeltzer of ANR will follow up
with the Town of Strafford and recommend where to improve ditches
and divert flow to keep it from mixing with the tailing. The
three starred locations are especially critical. In general,
ditches on the uphill side of each road should be improved.
- Slope Stabilization: I gave a copy
of the report on the 1989 NRCS plantings to everyone, they were
not familiar with it. Jason will check with John Dickerson
(NRCS) on exact locations of the test areas. As I remember,
the upper terrace plantings (no soil added, only fertilizer
and lime) is on TP2, but Jason will check with John. I remember
an area there with thick grass cover, but no one else did.
I recommended that since the best time to plant is September that
a pilot plot be hydromulched with the NRCS recommended seed mix,
10-10-10 and limestone as amendments. The best places for this
would be: the ditch at the base of TP1 on the west side (red line
on the map), the steep slopes of TP1 on the same side, and the steep
slopes of TP2. Any or all of these areas could be planted as a
test plot. The advantage of doing the ditch at the base of TP1
is that it is a critical area to stabilize, while mass failure of
the tailing pile on that side is not as much of a concern as failure
due to piping, or clogging of the adit, if that ditch was severely
eroded, it could undermine that side of TP1 causing failure. Hydro-mulching
this as a test plot is cheap (under $500 an acre for materials).
The county garage of VTRANS may be willing to donate the use of
a hydromulcher if they have one (most counties do, I believe).
I didn’t get any encouragement for doing test plots per NRCS recommendations,
but believe that a pilot project is cheap and would give good information.
Hydro-mulching could also be performed on all disturbed surfaces
as part of the emergency action. I strongly urge the CAG to request
that the ditch on the west side (red line) be hydro-mulched as part
of the emergency action, and the slopes of TP1 that are adjacent
to the ditch that will not be buttressed. If some money could be
saved on the emergency action (see comments below) than that could
free up some money for slope stabilization and hydro-mulching (which
can be justified as preventing erosion of tailing dam) under emergency
action.
- Diversion Pipe: I recommended that
some sort of active treatment be considered during construction
of the diversion pipe for the pond. It may be as simple as
spreading lime on top of the freshly exposed and disturbed tailings
(as ACE suggested), or it may be an active dosing system downstream.
Any construction brings an opportunity for acid shock, and typically
active treatment occurs during construction. The preliminary
drawings and description of the diversion pipe were presented.
The EPA said that the emergency folks are not usually too interested
in things like ‘acid shock’, but focus more on immediate threats.
3. Review Of Diversion Pipe Hydrology
And Design (To TAG By 8/22)
In summary, the diversion pipe is a 36 inch diameter plastic culvert
that is about 1000 ft. long. It will take the water from the base
of the pond, around the east side of the pile, and north to end
in the existing stream channel on the Northeast corner of TP1.
There will be some sort of energy dissipation (large rocks) installed
where the culvert meets the stream channel. The site will be accessed
either across TP1, or across the Jeep Road. If the Jeep Road is
used, it will be improved with an eye towards keeping the clean
part of the subwatersheds number 4 and 7 from mixing with TP1. The
Jeep Road is proposed as the ‘main drag’ to bring in buttress material
in 2004.
Parallel to the culvert will be ~1000 feet of 4 inch perforated
drain tile to intercept groundwater from the clean part of the watershed.
Both the 36” and 4’ pipe are proposed to be laid in washed sand
(See comments below) and will have clean-outs at regular intervals
(about every 300 feet). Most of the pipe will be fairly flat (0.5%
slope) for about 700 feet, and the last 300 feet will be at a 12%
(steep) grade. Both the culvert and draintile will be in a channel
that is graded flat and is about 15’ wide with 2:1 side slopes.
This wide channel will serve as a spillway for any flow that the
culvert can not handle (really big rain storms). The upper (flatter)
part of this ditch/spillway channel will serve as a road during
2004 for the construction of the buttress. The steep (12% slope)
part of the channel will be protected with rip-rap. This rip-rap
should probably be as big as possible (>20 inch diameter on the
middle (B) axis.), especially at the top of the slope to reduce
the chance of headcutting. The side slopes of the ditch.spillway
channel will be between 2:1 - 2.5:1 (pretty gentle gradient, not
liable to erode much). This means that (depending on existing topography)
that a swath of trees as much as 70 feet wide and 1000 ft. long
would have to be clear cut (about 1.7 acres). I don’t know what
the plans are for the cordwood/lumber/pulpwood that would be clearcut
from this area. Up to 7 ft. of glacial till will be excavated,
I imagine this will be stockpiled somewhere for use in berming/channel
diversions, but don’t know for sure. This entire trench will be
underlain with erosion fabric and appears to be filled with rip-rap
to a depth of 2 - 2.5 feet. This is a lot of rip-rap, thousands
and thousands of yards, I have not seen the spec sheets, but this
is a lot of stone. It appears that in the end (after the upper
part has been used as a road for the buttress) that the entire 1000
ft. of channel will be lined with rip-rap (because it is considered
a spillway), this may not be necessary if the stone at the top of
the steep slope is sized on the large side (to prevent headcutting)
at this vulnerable location.
The culvert and draintile are predicted to be part of the final
closure. The ditch/spillway channel may need re-grading or may
not be used as part of the final berms/diversion. Since the ditch/spillway
may not be part of the final closure I’d like them to look at an
alternative that may do the job effectively for the predicted period
of time of use (5 – 10 years). Perhaps the trench could be scaled
down (less rip-rap, no use of filter fabric etc) if the useful life
of this trench is relatively short. The money saved could go towards
hydro-mulching and small diversions as discussed above.
There is a limited area that will be re-graded near the base of
the pond to keep ‘clean’ water from mixing with tailings. The decant
system will eventually be closed, but a portion of it should remain
as a horizontal drain in TP1.
I’d recommend looking at down-sizing the ~35 ft. wide 12% grade
part of the channel. The bankfull widths of the existing stream
(downstream of the culvert under the tree) was around 7 feet. Since
steeper channels can be narrower (cause the water travels so much
faster), it may be possible to reduce the width of this channel
from 15’ with ~10 ft. of 2:1 slopes on either side of the 15’ channel
(unless it is being used as part of the road (which I doubt, but
is not clear in the design overview).
OTHER ITEMS DISCUSSED
Review of Field Sampling Plan:
URS will provide me with their comments on the Field Sampling Plan
soon. It appears that many of my comments have already been addressed,
and that some data has already been gathered.
Review of Passive Treatment report:
It
seems that there was general agreement that the passive treatment
report needed updating and that work is currently in progress.
We should receive it when it is complete. I recommended that since
URS does not have in-house capability for passive treatment, and
that - since it is likely that a Successive Alkalinity Producing
System (SAP) will be part of the final design -(per the EE/CA)
at TP1, that URS hire Damariscotta for the passive treatment portion
of the work. Damariscotta (as you may remember) invented the SAP
design, has over 20 years of experience with SAPS. URS currently
contracts with Damariscotta on another unrelated project.
COMMENTS:
Cost-Saving:
The CHC requested that I review the plans with an eye towards making
the best possible use of the money (3 million in emergency funding)
so that not only will the tailing pile be stabilized, but all possible
(justifiable) efforts to remediate the site be accomplished at the
same time.
In general, I think my biggest concern there is not in the design,
but in the details of the design. There are places where the Cadillac
version, might be able to be addressed with the Ford version. This
could free up money that could be used for more work that both addresses
remediation and emergency needs at the same time. I would request
that the CAG ask for an alternatives analysis that presents both
the Cadillac and Ford versions (ok. BMW and Volkswagen). I would
never suggest a design that has technical drawbacks, but there could
be some flexibility in the details that could reduce trucking costs
and truck traffic, two things that heavily impact the Town and the
overall cost of the project. An informal alternatives analysis
would help to address this, it could look at local stone vs. non-local
stone, local vs. trucked borrow, reductions in overhead and fixed
costs etc..
For example:
1) The plan is to bed both the draintile and 36”
culvert in washed sand. Washed sand (from Lebanon, NH) is $42 a
yard delivered. Typically in Vermont (calling on my many years
in construction) drain tile is bedded in peastone, and then covered
with hay, fiberglass insulation, old blue-seal bags, or a filter
fabric. It may be possible to limit the use of sand to the area
directly around the pipes and use stone or unwashed sand. Perhaps,
this type of alternative analysis could save money which could then
be used to scrape up more of the tailing fan at the base of TP1.
Scott Acone notes “Stone is not an acceptable substitute for
sand without additional measures to prevent the possibility of piping
within the backfilled culvert area. Compaction around large diameter
pipes is difficult. Sand backfill will prevent this piping. Other
measures such as installing concrete cutoff collars, would be necessary
with stone materials, and, will increase costs and truck traffic
associated with concrete trucks”. The sand also may not make
the best base for the road/spillway channel that will be taking
quite a bit of heavy truck traffic.
2) The channel for the culvert is 15’ wide, with
a 2:1 slope, and lined with rip-rap and native soil. The steeper
sections of the channel are lined with rip-rap. One option is to
limit the disturbance on the steeper section of the channel (so
that it doesn’t need to be so wide (unless it is part of the road)
and use rip-rap from stone quarried on or near the site. Since
water travels faster on steeper slopes, the size of the spillway
channel could possibly be reduced. No riprap has been specified
for the upper (shallower) channel at this time.
Rip-rap:
I called Dick Josler to see if
he was still interested in quarrying stone from his property, and
if the EPA et. al. had contacted him. The answer was yes, and no.
He hasn’t heard from the EPA, and he is interested in quarrying
stone. Quarrying local stone would save money in truck traffic,
wear and tear on roads, and support local people. I don’t know
if his stone would be the ‘best’ stone for the job, but if it is
not, there may be a trade-off with the reduced cost, reduced trucking
etc. There will be a lot of trucking, and a lot of stone required
for the buttress. Apparently the Superfund process trumps Act 250,
and material can be quarried for the project without an Act 250
permit, so that material could be quarried on this site this fall
if needed.
Local Contractors:
I asked ACE about using local contractors. Due to the nature of
the contracts, the contractor that they will use for managing the
construction associated with work is Conti Environmental based out
of Concord, Massachusetts. He has an established contract with
the Corps, has all the necessary bonding etc. He is likely to sub
out the work, and will likely hire local contractors. The project
will not go out to bid, but local contractors interested in the
buttress, diversion pipe etc.. should contact Scott Acone at the
Corps at 978-318-8162. I heard from Dick that there were several
contractors that would have liked to have had a chance to work on
the site.
Overhead and Fixed costs: These two costs;
overhead and fees are part of how the ACE does business.
Overhead costs (or the operating cost for the company to cover such
things as utilities, rent, administrative support, etc.) are determined
by an audit performed by the Government Accounting Office (GAO)
as part of this type of Corps’ contract. This rate varies annually
and is not negotiable.
Fee (or profit) is a negotiated cost for these contracts. Fee usually
ranges from 5% to 12% depending upon the complexity of work, the
type of work, the risk assumed by the contractor, and several other
factors discussed in the Federal Acquisition Regulations. Fee is
a necessary cost for Government contractors to cover costs excluded
from overhead by federal regulations (such as advertising and marketing)
as well as to provide incentive for the company to stay in business
and complete their work.
The Corps independently determines an appropriate fee for the work
being contracted and negotiates a fee rate with the contractor that
is in the best interest of the Government (i.e., is fair to all
parties).
My strongest recommendations are to:
1) Look carefully at existing roads to do
as much diversion as possible along existing roads. This is true
for EPA and the Town of Strafford.
2) Since it is unclear whether or not there will
be more money in the future, try to get the hydro-mulching/ slope
stabilization and removal of the tailing fan at the base of TP1
done under the emergency funding measures. Call it erosion and
sediment control.
3) Slope stabilization is especially critical on
the west side of TP1, that ditch/channel is a bit scary, very eroded.
Although failure on that side is not predicted, if that ditch washed
out, that west side of the pile could collapse contributing a huge
sediment load. The buttress will wrap around some of the west side,
but not the whole west side. I am not sure how they plan to deal
with the ditch at the base, we will see the plans for that this
winter sometime (is my guess). Stabilization of this ditch is a
high priority and should be funded under this action, including
stabilizing the slopes leading to this ditch/channel.
4) Look at the Ford version, perhaps locally quarried
stone (while perhaps not the best), may have trade-offs that will
make the project more affordable, and use more local resources (contractors,
local landowners etc…, that could reduce impact on town roads etc).
5) See if the CAG has any input on fixed fees and
overhead, and use of local contractors. This may free up money
for more implementation of slope stabilization and diversion.
6) Implement active treatment during construction
to avoid ‘acid shock’.
7) If the chemistry of the seeps can be preserved
(by not flowing over the tailings), than - using the air shaft
as a proxy - a lot of the loading from the seeps may be able to
be mitigated with oxidation and settling ponds at the outlet of
the seeps. My current understanding is that these ponds will be
part of the emergency measure.
8) Keep the culvert under TP1 (that exits by the
tree) and turn it into a horizontal drain. Since horizontal drains
will be part of this measure, it makes sense to keep an already
existing drain (it may need to be lined with perforated 4” tile
and seated in flowable fill.
9) Support stormwater mapping of culverts, ditches
and roads to see where low-cost improvements can be made to prevent
‘clean’ water from mixing with tailings.
10) Use Best Management Practices for Erosion and
Sediment Control (which may include hydro-mulching) areas of the
tailing piles that are eroding.
11) Request that the fee structure be set at the
lowest level of profit, thus ensuring more money for implementation.
I have friends who have been working on a large copper mine in Montana,
(for about 15 years now), and no remediation has been accomplished.
At this point - with funding unclear for future work, I recommend
that every possible action that could be conducted under the scope
of this emergency funding that could remediate the site (and be
justified) be implemented.
Scott Acone notes that “the scope of what the Corps can accomplish
is determined by EPA. For the emergency removal, only those activities
that go to eliminate the current risk to downstream residents are
considered within scope. Any cost savings associated with accomplishing
this effort will not necessarily go towards completing additional,
out-of-scope activities such as hydromulching and diverting surface
runoff along roadways….”
Let me know if you have any questions. I will get the final design
on the diversion pipe by August 22nd (when I get back from vacation).
I will try to comment on it at that point. Scott Acone’s comments
are incorporated into this version.
Lori
Loribarg@together.net
top
|
|