Estimated Truck Traffic Based on Conceptual
Design for Elizabeth Mine Stabilization Work
NOTES: 1. There is no design yet for the
buttress, therefore all estimates are conceptual and may be +/-
30% or more.
2. Larger, tractor trailer-type dumps could
be used to reduce the number of truck trips by roughly 30-50%.
This might require finding a route from Norwich other than Rte
132 to Mine Road, due to the sharp turn in South Strafford Village.
3. In addition, if an onsite source of stone
for crushing operations is identified, it may be across Mine Road
from TP1 and 2. In that case, we would look to use off-road, articulating
dump trucks to transfer material from beyond TP3 (possibly TP4
or near the South Open Cut) to TP1. These vehicles would likely
need to travel mile (+\-) on Mine Road to make this a viable option
for onsite stone. If we can:
4. At this time, it seems unlikely that sand
will be available onsite due to the geologic setting of the Elizabeth
Mine and the lack of significant sand deposits in the immediate
area.
DIVERSION PIPE (September thru October 2003):
* Sand (from West Lebanon, via Norwich Rte
5 to Rte 132 to Mine Rd) 900 cubic yards (about 1,700 tons) roughly
170 10-wheel dump truck loads, about 30 loads per day * Crushed
Stone (from Norwich via Rte 132 to Mine Rd unless produced onsite
with a crushing plant) 450 cubic yards (about 900 tons) roughly
90 10-wheel dump truck loads, about 30 loads per day * Concrete
(from West Lebanon, via Norwich Rte 5 to Rte 132 to Mine Rd) 100
cubic yards roughly 12 concrete truck loads over one day * Hydromulch
(from ???, assume Connecticut River Valley, via Norwich Rte 5
to Rte 132 to Mine Rd) Assume 5 trucks per acre. 1.5 acres will
be disturbed, 7 trucks over one day * Pipe, Equipment, Misc Supplies
(likely from Sharon via Rte 132 to Mine Rd) 20-30 trucks total,
mostly low-boy tractor trailer rigs or stake-body type trucks
* Daily Visitor and Site Personnel Traffic (likely from Sharon
via Rte 132 to Mine Rd) 10-20 vehicles (pickup, van, sedans) daily.
Arrive onsite by 7:00 am, depart from site around 5:00 pm, with
trips for lunch, local supplies, etc.
BUTTRESS (hauling of sand starting in November
2003, most significant work in summer 2004):
NOTE: This truck count assumes that NO general
fill for the buttress will be imported from offsite. The estimated
volume for this material is 48,400 cubic yards (97,000 tons).
This would amount to an additional 10,000 truck loads.
* Sand (from West Lebanon, via Norwich Rte
5 to Rte 132 to Mine Rd) 15,000 cubic yards (about 29,700 tons)
roughly 3,000 10-wheel dump truck loads, possibly 30-40 loads
per day over 3-4 months of hauling to build an onsite supply *
Crushed Stone (from Norwich via Rte 132 to Mine Rd unless produced
onsite with a crushing plant) estimated misc. volume for swales,
check dams, roads, pipe bedding, etc 1,500 cubic yards (about
3,000 tons) roughly 300 10-wheel dump truck loads, not likely
more than 20 trucks per day spread over the construction season
* Topsoil (from ???, assume Connecticut River Valley, via Norwich
Rte 5 to Rte 132 to Mine Rd) 10,000 cubic yards (about 20,000
tons) roughly 2,000 10-wheel dump truck loads, unless manufactured
onsite with borrow material and an organic amendment, then, only
organic material is trucked in at roughly 15% by volume, or 300
10-wheel dump truck loads. Likely about 30 loads per day to build
an onsite supply. * Hydromulch (from ???, assume Connecticut River
Valley, via Norwich Rte 5 to Rte 132 to Mine Rd) Assume 5 trucks
per acre. 7 acres will be disturbed, 35 trucks over several days.
* Horizontal drains, borings (likely from Sharon via Rte 132 to
Mine Rd)5 trucks, 2 drill rigs and 3 support trucks (twin axle
stake-body type). Support trucks will make daily trips over 2-3
weeks of drilling operations. * Pipe, Equipment, Misc Supplies
(likely from Sharon via Rte 132 to Mine Rd)100-200 trucks total,
mostly low-boy tractor trailer rigs and stake body type trucks,
spread out over the entire 18-month construction window. No more
than 5-10 trucks in any given day for deliveries, etc. * Daily
Visitor and Site Personnel Traffic (likely from Sharon via Rte
132 to Mine Rd)10-20 vehicles (pickup, van, sedans) daily. Arrive
onsite by 7:00 am, depart from site around 5:00 pm, with trips
for lunch, local supplies, etc.