|
FURTHER COMMENTS
Wetland treatment concepts in EPA/A.D. LITTLE
draft Engineering Evaluation/Cost Analysis (EE/CA) Report on the
Elizabeth Mine
This report is intended to describe the discussions
at a meeting on November 7, 2001 between myself, Richard Downer,
Cindy Clark, and representatives of the State of Vermont, the EPA,
the Corps, A.D. Little, and various other federal agencies and expert
consultants (a total of 12 individuals) This group had been assembled
by EPA/AD Little to take a final look at the problem and the proposed
alternatives and to insure that all critical factors have been considered
and included prior to publication of the final EE/CA in December.
The group had spent the day visiting the Elizabeth Mine site, our
meeting convened at 3:30 that afternoon and was in essence an open
discussion of any remaining issues. The meeting adjourned at 6:00
PM.
Most of the visitor participants were concerned
with the geotechnical aspects of construction and the capping alternatives,
since these are Richard Downer's area they will not be discussed
in this report. One of the consultants was Mr. Robert S. Hedin,
who was there to consider the "passive" treatment system proposals.
I had known Bob previously and have a great deal of respect for
his expertise and his opinions. He is one of the earliest proponents
of wetland treatment for acid mine drainage, and is President of
his own firm in Pittsburgh, PA. After inspecting the site and reviewing
the available preliminary data he believes that the seepage from
TP 1-2, because it is relatively low in aluminum, has a "moderate"
pH, and some alkalinity, would be amenable to treatment with a wetland
(for final polishing) preceded by either an anoxic limestone drain
(ALD) (which is briefly mentioned in the EE/CA draft report and
is described in my first report of 10/03/01), or successive alkalinity
producing systems (SAPs) (also described in the draft EE/CA report
and my report of 10/03/01), or sulfate reducing bacteria systems
(SRBs) as proposed by Mr Jim Gusek (another ADL consultant). The
SRB concept was not included in the draft EE/CA report, but is described
in my second report (10/15/01). The choice of the best option should
depend on collection of further data and pre-design pilot testing.
In Mr. Hedin's opinion the seepage from TP 3 presents a far more
complex and difficult to treat problem; the seepage is highly acidic,
and contains high concentrations of aluminum and iron. Under these
conditions, neither the ALD or the SAP may be appropriate and maintenance
requirements might be very high for the SRB, and continue for many
, many years. The most positive approach to this critical problem
would be to either remove the TP 3 tailings or cap them.
It is my assessment that Mr. Hedin's proposals,
and opinions, rank somewhere between the draft EE/CA and the proposals
by Jim Gusek (see my report of 10/15/01 for a description of these).
I would agree that the seepage from TP1-2 can be adequately treated
with either an ALD, or a SAP, or a SRB as the initial treatment
unit. The final selection will depend on sizing requirements and
on operation and maintenance costs. Sizing will only be possible
after further data is collected and possibly pilot testing, so the
EE/CA report should include information on all three concepts as
potential alternatives. The operations and maintenance requirements
are a critical issue since the State of Vermont must accept responsibility
for these aspects. The wetland component, as used in the passive
treatment system, have been in use for many decades and do not require
frequent cleaning or similar maintenance. An ALD may require replacement
of the limestone media every 50 years, The SAP is claimed to require
media (compost & limestone) replacement every 12 to 15 years, and
a flushing of the media every 6 to 8 months. The SRB, according
to Jim Gusek, would require only media (cattle manure & limestone)
replacement every 25 to 35 years. These media replacement estimates
are theoretical estimates since none of these concepts have been
in routine service for more than five or six years. This is an important
issue for both the State of Vermont and the community residents
since media replacement will require expenditures by the State and
contract truck traffic for removal and replacement of the material.
If TP 3 is maintained in it's present condition for historical reasons
this maintenance requirement could persist for generations. If TP
1-2 are properly capped and seepage reduced to a minimum , the useful
life of the treatment components could be extended and long term
replacement maintenance possibly reduced to a reasonable period.
Based on my experience with estimates of this type I believe the
25 to 35 years for the SRB and the 15 years for the SAP may both
be too optimistic. I would suggest more conservative values be adopted
for planning purposes, say 15 years for the SRB and 10 years for
the SAP. Flushing, twice a year for the SAP would also be a conservative
assumption at this point. It is unclear, at this point if similar
flushing might be required for the SRB.
The draft EE/CA report only mentioned ALDs
in passing, and clearly indicated that SAPs would be used to treat
both TP 1-2 and TP 3 seepage. At the later meeting with Jim Gusek
and EPA/ADL the impression was then clearly established that SRBs
would be used instead of SAPs and my report of 10/15/01 described
this change. However, as indicated by Mr Hedin at this most recent
meeting it is premature with the limited data we now have available
to make a final selection of the preferred technology. I concur
in this opinion. As a result, the final EE/CA report will present
all three alternatives for possible use at TP 1-2. However, the
costs presented in the draft EE/CA report may not be changed. These
are preliminary estimates, typically valid within 25% to 30% of
the actual costs, and are believed conservative enough to cover
any of the various alternatives, with two exceptions. The operation
and maintenance costs are based on a once per year flushing of a
SAP and a 15 year replacement cycle. These costs would increase
if the more conservative schedules I recommended previously are
adopted. The final selection of the treatment process components
will occur in pre-design following analysis of additional data and
possibly pilot testing.
Now that ALDs and SAPs are back in consideration,
the concern I expressed in my report of 10/03/01 regarding winter
ice formation on the wetland is also back in the picture. There
has apparently been some confusion on this point. It is true that
biological and some chemical reactions slow down during cold weather,
but I am not concerned about that as an issue. You compensate for
those problems, during design, by making the wetland larger for
winter service. My concern relates to the formation of ice on the
wetland. With the ALD and SAP concepts the iron is expected to oxidize
and precipitate in an "aerobic" wetland. In most months of the year
with an "open" water surface this will not be a problem and will
happen automatically. In the coldest part of the winter however,
there will be a continuous ice cover on the wetland, with the oxygen
source from the atmosphere cut off the wetland will no longer be
"aerobic" and may no longer remove the iron to a satisfactory degree.
You can't solve this problem by making the wetland bigger, that
results in the water getting colder and the ice getting even deeper.
In a really cold winter, without a snow cover, we might get up to
three feet of ice on ponds and wetlands. The seepage coming out
of the tailings piles should be about 44°F during the winter months
so ice formation on all exposed water surfaces can be expected every
winter. Mr Hedin agreed that this aspect must be considered during
predesign for the Elizabeth Mine. He indicated that systems in Pennsylvania
have no problems with achieving water quality goals in the winter,
but the climate there is milder and more variable than we experience
here in Vermont. My concern on this issue is based on my personal
experience, and that of others, with wetland systems in Canada.
Sherwood
C. Reed, P.E.
Principal, E.E.C.
top
|