The following summarizes the NTCRA
work completed on the Elizabeth Mine Superfund Site for week
ending Friday, 4 August 2006:
Hauled in bank run gravel (120 cubic yards
(CY) for a total of 2002 CY), rip rap (1933.6 tons for a total
of 3452.9 tons) and manure (362.5 CY for a total of 955.5 CY).
Mobilization of heavy equipment to the Site including two articulated
dump trucks, two excavators and a loader.
VTDEC, EPA, USACE, and URS reviewed the layout of a new access
road and the surface water channel extension from Sta. 23+00
(past the existing access road below buttress) to Copperas Brook.
Surveyed proposed the channel extension from Sta. 23+00 to
Copperas Brook
Removal of sediment from the existing sedimentation ponds.
The removed sediment was placed on top of TP-1.
Began clearing of the new access road and the channel extension
from Sta. 23+00 to Copperas Brook
Installed water bars on Copperas Road.
Installed orange construction fence around the mine shaft of
the south mine.
The stabilized construction entrance off Mine Road to new access
road.
Continued the layout of the center line of the drainage swale
from Sta. 12+00 to 23+00.
The following work is anticipated between August 7 thru August
11:
Delivery of additional heavy equipment
(bulldozers, articulating dump trucks).
Delivery of additional material (rip rap, wood chips).
Approximately 25 truckloads of riprap each day.
Continue clearing of the access road and the channel extension
from Sta. 23+00 to Copperas Brook.
Clear, grub, excavate and install channel stabilization materials
of Sta. 23+00 to Copperas Brook.
Start the chipping of the trees.
Begin regrade of west side of TP-1.
Investigation of the sink hole.