UNITED STATES ENVIRONMENTAL PROTECTION
AGENCY
REGION I
ONE CONGRESS STREET SUITE 1100
BOSTON, MASSACHUSETTS 02114-2023
March 19, 2003
Elizabeth Mine Community Advisory Group
c/o Robert Walker, Chairperson
432 Ulman Rd.
Thetford Center, VT 05075
Dear EMCAG:
Recent work by the United State Environmental Protection Agency
(EPA) indicates that there is the potential for the large tailing
pile (a pile of processed rock often referred to as "TP-1")
at the Elizabeth Mine Superfund Site to release a tailing flood
wave (a large mudslide) that could threaten low lying areas of the
West Branch of the Ompompanoosuc River. EPA has sent letters to
notify those individuals living in homes that have been identified
as being within the impact zone. EPA will be presenting more information
regarding this matter at EMCAG meeting scheduled for Wednesday,
April 9th at 7:00 p.m. at Barrett Hall in South Strafford.
I want to preface the following information with the fact that TP-1
has been abandoned and intact since 1958. While recent findings
by EPA raise serious concerns regarding the stability and long-term
integrity of TP-1, it is impossible to predict whether TP-1 will
continue to remain intact as it has for 45 years. It is also impossible
to predict when conditions will worsen resulting in the consequences
described in this letter. It is quite possible that Site conditions
will not deteriorate to the point that a failure of TP-1 occurs.
After careful consideration of the information available, including
the possible consequences of a tailing dam failure, EPA and VTDEC
believe that there is a need for immediate action to significantly
reduce the potential for a slope failure and tailing flood wave.
We have notified the local authorities of the situation and will
be coordinating our efforts with them.
What is being done to minimize the hazard?
- EPA and VTDEC have begun monitoring the Site to identify any change
in Site conditions and to provide notice to local authorities if
conditions change.
- VTDEC will be installing debris racks to reduce the potential
for material to enter and block the decant system (the decant system
consists of concrete piping that currently drains surface water
off the tailing pile).
- EPA will install pumps to reduce the water level on TP-1 in the
event that the decant system were to become blocked or collapse.
- EPA will repair the internal dam erosion (piping) of material
out of the tailing dam as soon as possible.
- EPA is seeking funds to install a temporary surface water diversion
system to replace the need for the pumps and to install a more permanent
surface water diversion system to divert surface water around TP-1.
With these measures, EPA and VTDEC will have implemented all reasonable
precautions to minimize the chance of a tailing dam failure. EPA
and VTDEC will also be working with local authorities to provide
regular updates regarding Site conditions and to assist in the development
of an emergency response plan.
I have attached additional information to better explain the circumstances
at the Site and the basis for the concern expressed by EPA and VTDEC.
Please read this information and feel free to come to the meeting
or call and ask questions. For information about the emergency response
plans associated with this situation, please contact your local
Emergency Management Director or Selectboard.
You may also contact Ed Hathaway, US EPA at (617) 918-1372 or toll
free: 1-888-372-7341 ext. 91372,email address: hathaway.ed@epa.gov
or John Schmeltzer, VTDEC at (802) 241-2886 and email:johns@dec.anr.state.vt.us
if you have any questions regarding the activities at the Site.
Sincerely,
Edward Hathaway, RPM
ME/VT/CT Superfund Section
Attachment 1
Information Relating to the Geotechnical/Stability Concerns at the
Elizabeth Mine
March 2003
The information below provides a detailed explanation of the five
factors which contribute to the identification of TP-1 as a significant
hazard, and why EPA is concerned about the stability of TP-1.
The first is the nature of the material contained within both TP-1
and TP-2. The tailing material was generated during the copper mining
of 1942 - 1958. The tailing material behaves like a silt material
such that when saturated or exposed to water, it becomes suspended
and flows with the water. The tailing slurry was deposited at the
downstream edge of TP-1. This caused a physical separation of the
tailing slurry. The more coarse-grained, better draining, material
was retained along the outer edge of the tailing pile and the higher
water content, less well draining material accumulated within the
interior. The end result is that the outer well drained material
forms the dam that holds back the other material. A breach in that
outer dam portion of TP-1 would result in the release of the fine
grained material and this material would flow with the water released
from TP-1. TP-1 covers over 30 acres and contains approximately
2 million cubic yards of material, most of which is the fine grained
weaker material.
The second factor is the deteriorating drainage system for TP-1.
The entire 300-acre upper Copperas Brook watershed drains on to
TP-1 and flows through a deteriorating drainage system designed
and built in the 1940's and 1950's as a decant system for the tailing
slurry deposition. Recent video inspection of the decant system
revealed it to be in poor condition with cracks and partial blockage
due to encrustation and debris. It is reasonable to assume that
at some point in the future the decant system will cease to function
and significant quantities of water will accumulate on top of TP-1.
The third factor is the potential problem that could arise once
the drainage system is no longer functioning. If the decant system
were to become blocked or to collapse due to deterioration, water
would pond on the surface of TP-1 with three potential negative
consequences.
1. An increase in the water level on TP-1 would result in additional
infiltration into TP-1 with a resulting rise in amount of water
stored within TP-1. A five to fourteen foot increase in the water
table within TP-1 could cause internal instability that could result
in a slope failure and massive release of tailing material.
2. There is currently internal erosion of the tailing dam. Internal
erosion, also known as piping, occurs when fine material from within
the pile is carried out with seepage and causes a sinkhole, which
can collapse and cause failure of the dam. An increase in the water
level within TP-1 will create more internal erosion, which increases
the chance that the internal erosion will result in a slope failure
and massive release of tailing material.
3. If the water on top of TP-1 were to increase to a level where
the water overtopped TP-1, the resulting erosion could result in
a slope failure and massive release of tailing material.
The fourth factor is the behavior of the tailing material once the
tailing dam is breached through slope failure, internal dam erosion
(piping), or overtopping. Based upon experiences at other similar
sites and computer modeling results evaluating these types of events,
a preliminary estimate of a tailing dam failure and release at the
Elizabeth Mine suggest that between 500,000 and 1,000,000 cubic
yards of tailing could be released depending on the actual breach
geometry and the amount of water in the decant pond at the time
of the failure. The resulting flood wave would be eight to nine
feet high and travel at a velocity of 10 - 15 feet per second (7-10
miles per hour). The flood wave would travel a distance of one to
five miles from the Site with a significant quantity of tailing
material being transported from the confluence of Copperas Brook
and the West Branch of the Ompompanoosuc River into the Connecticut
River. The fifth and final factor (and most critical factor) in
identifying the potential failure of the tailing dam at the Elizabeth
Mine as a significant hazard is the potential impacts to human health
and the environment. There is a serious concern that a tailing flood
wave could overtop the West Branch of the Ompompanoosuc River in
the low lying sections between Copperas Brook and Rices Mills. Many
structures impacted by the flood wave would be seriously damaged,
potentially threatening the lives of any occupants of those buildings.
Ten to fifteen structures have been identified within the potential
impact area of a tailing dam failure. The environmental impacts
of the release would also be severe with the potential for a major
fish kill and high metal/low pH conditions in the impacted stretch
of water for an extended period of time (possibly tens of years).
The environmental impacts would extend from Copperas Brook to the
Connecticut River and possibly into the Connecticut River.
Attachment 2
Additional Technical Information and Definitions: This information
was obtained from the website: http://www.antenna.nl/wise/uranium/mdas.html#WATERLEVELRISE
and site specific facts were added as deemed appropriate.
Tailing: Tailing are the residue of the milling process that is
used to extract metals of interest from mined ores. During this
process, ores are first milled and finely ground, and then treated
in a hydrometallurgical plant. Since the extracted metal represents
only a small percentage of the whole ore mass, the vast majority
of the material mined ends up as a fine slurry. The tailing contain
all other constituents of the ore but the extracted metal, among
them heavy metals and other toxic substances. Moreover, the tailings
also contain the chemicals added during the milling process. In
addition, as a result of the milling process, all these contaminants
now are much better available for dispersion into the environment
than in the original ore. The mechanical stability of the tailing
mass is very poor, due to its small grain size and the usually high
water contents.
Tailings impoundments: Most of the mill tailings mass produced worldwide
is dumped in large surface impoundments ("tailings dams").
The embankments forming these impoundments are earthfill dams. Although
water-retention type dams would be very suitable for tailings dams,
they are not used for their high cost. Unlike water-retention type
dams, tailings dams usually are not constructed initially to completion,
but raised sequentially as the impoundment fills. At the Elizabeth
Mine, TP-1 and TP-2 are tailing dams.
Upstream Tailing Dams: TP-1 and TP-2 were constructed as Upstream
Tailing Dams: Upstream-type embankments are the most popular embankments
for tailing dams; new parts of the embankment are built on top of
the slurries impounded during the previous stage - the dam crest
thus moving "upstream". For its low cost, the upstream
embankment type is used with most tailings dams worldwide, but it
bears the highest risk. Dam stability is of particular concern with
this type of tailings embankments. Upstream dams are particularly
susceptible to liquefaction under severe seismic ground motion.
This motion may result from earthquakes, from nearby mine blasting,
or even from nearby motion of heavy equipment, for example. Upstream
dam stability is endangered if the raising rate of the dam is too
high. Raising rates greater than 15 m/yr can be hazardous. They
can produce excess pore pressure within the deposit, decreasing
stability.
Phreatic Surface: ?The phreatic surface is critical for the dam
stability. Dam failure can occur, if the beach width between the
decant pond and the dam crest becomes too small - from flood inflow,
or from improper mill operation, for example. While the determination
of phreatic surface location is so important for upstream-type embankments,
it is more complex by far for this embankment type than for any
other type of tailings-retention structure.
top
|
|